The logs are configured with unrestricted growth mode. Else ensure that you have provided
sufficient space for the logs to grow.
We have observed the logs to grow by 20GB when migrating the vCenter Chargeback Manager
database with 100 million rows in our test environment.
n
The Stats Synchronization job of all the data collectors for each vCenter Server added to vCenter
Chargeback Manager is completed successfully before you start the upgrade. You can check the
status of the job from Settings > Data Collectors > Chargeback Manager in vCenter Chargeback
Manager.
n
The database user has the necessary privileges to run the database partitioning scripts. See
“Database Management Prerequisites,” on page 16 for the list of required database privileges.
What to do next
Back up the relevant configuration files from the current vCenter Chargeback Manager installation, so that
you can restore the existing installation if the upgrade fails. See KB 1026796
(http://kb.vmware.com/kb/1026796) for further details.
Upgrade vCenter Chargeback Manager
You can upgrade an existing vCenter Chargeback Manager instance to a more recent version.
Prerequisites
Before you upgrade a standalone vCenter Chargeback Manager instance, stop the corresponding vCenter
Chargeback Manager service and the data collector services. If any vCenter Chargeback Manager related
service is running, the upgrade process fails. If the load balancer and the vCenter Chargeback Manager are
on different machines, then first run the installer on the load balancer machine to upgrade the load-balancer
and the vCenter Chargeback Manager database. You must then run the installer on the vCenter Chargeback
Manager server machine to upgrade vCenter Chargeback Manager instance.
For a cluster installation, you must upgrade each vCenter Chargeback Manager instance in the cluster. You
must first upgrade the instance that has the load balancer. Before upgrading the first instance of a cluster,
you must stop all the related services. When the first instance is upgraded, the corresponding vCenter
Chargeback Manager database is also upgraded. After the upgrade, the vCenter Chargeback Manager
service and the corresponding database, data collector, and load balancer services are automatically
restarted.
NOTE You must upgrade all the instances in a cluster to ensure that the application functions correctly. A
cluster with multi-version vCenter Chargeback Manager instances might not function correctly.
Ensure that you are running the installer on the machine on which vCenter Chargeback Manager is
installed. If you run the installer from a shared location on the network, the installer might fail.
If the existing instance vCenter Chargeback Manager has a vCloud Director data collector installed, ensure
that you provide the same vCloud Director database details for the vCenter Chargeback Manager instance
during upgrade.
Procedure
1 Run the vCenter-CB.exe file.
The installation wizard is displayed.
2 Click Next on the Introduction screen.
3 Accept the end-user license agreement, and click Next.
When the installer detects an older version of vCenter Chargeback Manager, an Alert dialog box is
displayed.
vCenter Chargeback Manager Installation and Upgrade Guide